Progress

The project officially started on January 1st, 2012 and it will be accomplished in 24 months, by December 31th, 2013.

The Kick-off Meeting held in Heraklion on February 2012.

The project meetings and the WPs progress are presented below:

General Activity:

 

Meeting

Date

Minutes

Kick-off Meeting

February 8, 2012

GEOURBAN ftp Server

1st Management Board Meeting

February 8, 2012

GEOURBAN ftp Server

BaselCoP Meeting

April 25, 2012

GEOURBAN ftp Server

2nd Management Board Meeting

May 11, 2012

GEOURBAN ftp Server

Tel-Aviv CoP Meetingh

May 16, 2012

GEOURBAN ftp Server

Tuymen CoP Meeting

July 23, 2012

GEOURBAN ftp Server

1st Progress Meeting

July 23-24, 2012

GEOURBAN ftp Server

3rd Management Board Meeting

July 24, 2012

GEOURBAN ftp Server

4th Management Board Meeting (SKYPE)

Sep 14, 2012

GEOURBAN ftp Server

5th Management Board Meeting (SKYPE)

Nov 2, 2012

GEOURBAN ftp Server

Mid-term Meeting

Dec 13-14, 2012

GEOURBAN ftp Server


Work Packages Activity:

WP2     Concluded                  GEOURBAN ftp Server

WP3     Active                       GEOURBAN ftp Server

WP4     Active                        GEOURBAN ftp Server

 WP5     Active                      GEOURBAN ftp Server

WP6    Active                       GEOURBAN ftp Server

WP7     Active                      GEOURBAN ftp Server

WP8     Active                      GEOURBAN ftp Server

WP9     Active                      GEOURBAN ftp Server